Marine Notice 64 of 2019 - Erne System - Upper Lough Erne - Kilmore Quay - Dredging operations - From 01 July 2019 for 9 weeks

Notice Number 64 of 2019

MARINE NOTICE
No. 64 of 2019

Erne System

Upper Lough Erne – Kilmore Quay

DREDGING OPERATIONS AT KILMORE QUAY

Waterways Ireland wishes to advise Masters and owners of vessels that dredging works at Kilmore Quay are due to commence on the 01st July 2019. The duration of the works is approx 9 Weeks.

The map below shows the area to be dredged and the route the vessels will be taking in order to bottom dump the material.

 
Masters of vessel are requested to proceed with additional caution in the vicinity of the dredging operations and dredging vessels.

Waterways Ireland thanks its customers for their cooperation in this matter.


P Harkin
Inspector of Navigation
21 July 2019
Tel: 00 353 (0)90 6494232