
Waterways Ireland is entrusted with restoring approximately 13.5km of navigation from Upper Lough Erne, Co. Fermanagh to Clones, Co. Monaghan. The work is divided into three phases, two of which are complete. Waterways Ireland has established a dedicated project team to deliver Phase 3.
The third phase of Waterways Ireland’s restoration of the Ulster Canal has been initiated. This is the largest phase and runs from Castle Saunderson to Clonfad, approximately 10km. When completed it will allow the navigation of 14,5 all the way from Clones in Monaghan to the mouth of the Shannon in Limerick, passing through Lough Erne.
The project includes 10km of new and refurbished navigable canal and towpath with a looped walk and amenity area, a sustainable water source, a double lock chamber and marina at Gortnacarrow. Key infrastructure to be delivered also includes seven new bridges (one will be a lifting bridge), a small footbridge and refurbishment of three existing masonry arch bridges, culvert, and drainage repairs, stop gates provision of a new service block facility and carparking.
The project will be delivered in four sub-phases. Phase 3.1 and 3.2 from Castle Saunderson to Gortnacarrow to Clonoony will provide an additional 2.5km of navigable waterway and a new destination marina at Gortnacarrow. These phases are progessing first. Outline designs for Phase 3.1 and 3.2 infrastructure, including the canal, bridges, locks, marina, service block and parking areas have been completed. A detailed design tender issued in April 2025 for the 3.1 and 3.2 sections of Phase 3.
ULSTER CANAL PHASE 3
|
|---|
Phase 3.1 – Castle Saunderson to Gortnacarrow (2km)
- New underpass bridge Wattlebridge
- Carparking area at Wattlebridge
- 1km Finn River dredging for 2km of navigation
| Phase 3.2 – Gortnacarrow to Clonoony (0.5km)
- New A3/N54 road bridge
- New access bridge
- Water supply infrastructure
- Double lock chamber
- Gortnacarrow Marina
- 0.5km of canal restoration
| Phase 3.3 – Clonoony to Derrynure (3.75km)
- New Drumsloe road bridge
- Existing Kelly's Bridge refurbishment
- New Clonlura pedestrian footbridge
- Existing Cloncorrick Bridge refurbishment
- 3.75km of canal restoration
| Phase 3.4 – Derrynure to Clonfad (3.75km)
- New Derrynure access bridge
- New Clongowna access bridge and stop gates
- New Munnilly lifting bridge
- Munnilly amenity area
- Existing Munnilly Bridge refurbishment
- 3.75km of canal restoration
|
Planning permission is in place for the County Fermanagh sections of the project. Planning permission has been re-applied for in Monaghan as it was originally granted in 2013 and lapsed after 10 years. The application is currently with Monaghan County Council awaiting a decision during 2026.
Waterways Ireland is engaging with the landowners in both Fermanagh and Monaghan along the canal restoration route. Where vesting is required in Fermanagh it will be undertaken by the Department for Infrastructure. CPO will be undertaken in Ireland once planning permission is received.
Funding is in place to complete 3.1 and 3.2 – from Castle Saunderson to Gortnacarrow to Clonoony - providing an additional 2.5km of navigable waterway and a new destination marina at Gortnacarrow. The funding currently committed will allow us to advance the remainder of Phase 3.
Additional information about the project’s progress will be posted here as it becomes available.